Home    xmlfeed    submit articles    sitemap    privacy    links    contact us    terms    submission guidelines
RSS Feeds Add us to favorites
Make us your home page
Free Newsletter
Subscribe to newsletter
Sponsors
  • Complete eBusiness Automation
  • sponsor iPAYworld.com
  • Worlds Leading Internet Marketing Membership Site
  • sponsor Internet Advice Center ®
  • Private Label 'Sponders
  • sponsor WebsiteHitMachine.com
  • 32 World Leading Experts Reveal All
  • sponsor Light Speed Profits.com
  • Earn Dollars for your Clicks... not cents!
  • sponsor Bizoot!
    Categories
    Home Business
    Small Business
    Health & Fitness
    Self Improvement
    Money & Finance
    Computers & Technology
    Kids & Teens
    Arts & Entertainment
    Home & Family
    Womens interests
    News & Society
    Religion
    Travel & Leisure
    Sport & Recreation
    Automotive
    Cars
    Education & Reference
    Food & Drink
    Internet Marketing
    Affiliate Marketing Email Marketing
    Recommended Products


    Difference Between Calendar Days And Work Days
    Author: Mukul Gupta
    Website: www.script2please.com
    Added: Sat, 31 Mar 2007 13:38:55 -0700
    Category: Computers & Technology
    Printable version | Email | Bookmark

    Don’t people already know this? Well seems like “Not everybody!”

    Both seasoned IT entrepreneurs as well as developers make this common mistake. They don’t seem to quite understand the difference between calendar days and work days. So let me ask you this question – “What should be the delivery date of a project starting on October 1st and having an estimated effort of 160 hours?”

    A typical calculation goes like this:

    160 hrs / 8 hrs per day = 20 days. So, if the project is starting on October 1st, it should all be done on 21st October. Right? Wrong!

    Here is what is involved, in understanding the delivery date based on start date and total number of hours that is required to accomplish the task:

    Number of Days per Week: This is the number of days for which the office of the developer’s organization is going to be open in a week. It can be any number from 5 – 6. Like some companies are open for half time on Saturday. So, this figure is 5.5 for such an organization.

    Number of Hours per Day: This signifies, the number of normal work hours that developer will be working in particular day. Do not take overtime in account because then you will not have any buffer to use should the project slip.

    So, based on the above two numbers, if the Number of Days per week is 5 and the number of hours per day is 8 then the developer is going to work 8 hours per day then you will 8 X 5 = 40 hours of work done per week.

    This means it will take 4 weeks to get 160 hours of work done. This is an equivalent of 28 calendar days which means that given a project started on 1st October it cannot be completed before 28th October.

    Granted, that the above calculation is very simple, but you get the message! In reality, things are more complex because the utilization of hours depends on other factors like Number of resources on the project, Number of parallel tasks, Holidays etc.

    Why knowing this is important?

    Knowing this is very important for two very important reasons:

    1. It forces you to plan in advance. As you try to think about delivery dates, you automatically begin thinking about the things that affect it.

    2. It prevents unnecessary dissatisfaction. Had you not known this, the delivery on October 28th would haven perceived as a 25% slippage in project deadline whereas the developer has been able to meet the deadline.

    About Author:
    Mukul Gupta is the CMO of Indus Net Technologies, an India based Internet Consulting firm which specializes in Opensource solutions. You can reach him at script@script2please.com or visit http://www.script2please.com

    View all Mukul Gupta's articles


    About the Author:
    Mukul Gupta is the CMO of Indus Net Technologies, an India based Internet Consulting firm which specializes in Opensource solutions. You can reach him at script@script2please.com or visit http://www.script2please.com

    More Computers & Technology articles


    :- Articles Search

      
    Search our article database!

    :- Recent Articles
    The Real ‘Magic Bullets’ of Internet Marketing.
    The Million Dollar Idea Maker
    10 Ways to SCREW-UP your List
    How to Catch a Cheating Lover
    10 Tips to Avoid Band-Wagon Business
    Buyer BEWARE
    Creating the Right VIRAL Reputation
    Do you REALLY believe?
    Fail to plan Or Plan to FAIL
    Failure IS an option
    Interview with Experts - Part 1
    Interview with Experts - Part 2
    Reselling Resold Resale Rights
    The Jigsaw Virus
    What is Arbitrage Investment
    Wake Up HOMER SIMPSON
    P M A
    Latex Foam Mattresses: A Healthy Alternative to Memory Foam
    Elements of Timeless Leadership
    12 Reasons to Market With Postcards

    :- Top Resources


    Copyright 2005 / 2006 ArticleAlliance. All Rights Reserved.